How Much Does Furnace Replacement Cost?
Replacing a furnace typically costs $3,500–$6,000 installed for a single-stage 80% AFUE gas unit, and $4,500–$8,500 for a high-efficiency two-stage unit, at national-average prices in 2026. Most homeowners pay around $5,000–$6,000 for a straightforward like-for-like gas furnace swap. Those ranges cover the equipment, installation labor, venting and gas or electrical connections, old-unit removal, permits, sales tax, and a 10% contingency. Complex jobs — fuel switches, ductwork fixes, or high-efficiency retrofits — can run past $10,000.
This guide covers furnace-only replacement costs by type and efficiency, what drives the price, and the items quotes most often leave out. If you are replacing the whole heating and cooling system at once, the numbers are bigger: our calculator puts a complete HVAC system replacement at about $11,500–$16,000 for a typical 3-ton system. For a number based on your home, use the HVAC cost calculator.
Cost at a glance
| Furnace type | Typical installed cost |
|---|---|
| Electric furnace | $2,000–$4,500 |
| Gas, single-stage (80% AFUE) | $3,500–$6,000 |
| Gas, two-stage (92–96% AFUE) | $4,500–$8,500 |
| Gas, modulating (96–98% AFUE) | $6,000–$10,000+ |
| Oil furnace | $4,500–$9,000 |
Ranges are national averages with labor, permits, disposal, sales tax, and a 10% contingency included. Labor rates in your metro can move them 10–40% either way; see how we calculate costs.
What's included in the price
The equipment itself usually runs $2,000–$5,000; the rest is labor and materials. A complete quote should include:
- The furnace — sized by a Manual J load calculation (the industry-standard sizing method), not a rule of thumb based on square footage.
- Removal and disposal of the old unit — typically $50–$250, and should be line-itemed rather than assumed.
- Venting — high-efficiency condensing furnaces vent through PVC pipe and need a condensate drain; standard furnaces use the existing flue.
- Gas line or electrical connection — reconnecting the gas supply, or a new dedicated circuit for electric models.
- Ductwork connections and sealing — tying the new furnace into the existing supply and return plenums.
- Thermostat and commissioning — wiring the thermostat (often a good moment to add a smart thermostat, $150–$350) and testing combustion, airflow, and safety controls.
- Permit and inspection — usually $250–$500; required in most jurisdictions.
What drives the cost up or down
Efficiency (AFUE). AFUE tells you what share of fuel becomes heat: an 80% AFUE furnace wastes 20% up the flue. Stepping up to 95% or higher typically adds $1,000–$2,500 upfront and can cut heating bills noticeably in cold regions. The highest-efficiency units also vent through PVC instead of a chimney, which changes the venting scope.
Staging. Single-stage furnaces run full-blast or off. Two-stage and modulating units adjust their output to the weather, run quieter, and hold temperatures more evenly — for a premium of roughly $1,000–$3,000 over a single-stage unit of the same efficiency.
Fuel type. Natural gas units are the most common and cheapest to run. Oil furnaces cost more to install, and fuel prices swing with the market. Electric furnaces are the cheapest to install but expensive to run in cold climates, where heating is mostly what the electric bill becomes.
Size. An undersized furnace can't keep up on cold nights; an oversized one short-cycles, wears out faster, and costs more to buy. Proper sizing comes from a Manual J load calculation — any contractor who sizes by square footage alone is guessing.
Ductwork and venting. If your ducts are leaky or undersized, expect $2,000–$5,000 in modifications — the most common budget surprise on this job. High-efficiency condensing furnaces must not vent into an old masonry chimney without a proper liner; shortcuts here are a carbon-monoxide risk.
Gas line and electrical. A new gas line run typically costs $300–$1,000; a dedicated circuit for electric models runs $200–$500. If the panel is nearly full, that circuit can trigger a bigger job — see how much an electrical panel upgrade costs.
Labor market. Installer rates vary widely by metro, and winter emergency replacements carry a premium. Get at least three quotes.
What quotes often leave out
Before you compare bids, check that each one covers:
- A written scope with the AHRI reference. For matched systems, ask for the AHRI certified reference number proving the components are rated to work together, plus the efficiency ratings in writing.
- Manual J load calculation. If a quote sizes the furnace without one, that is a red flag.
- Permit and inspection. Sometimes left off lowball quotes and added later ($250–$500).
- Condensate drain and flue liner work. High-efficiency furnaces produce acidic condensate that needs a drain; old chimneys need liners before reuse.
- Duct sealing or repairs. Legitimate in older homes, but get the scope in writing — this is where vague quotes balloon.
- Warranty terms on parts and labor. Ten-year parts and labor terms exist; know what you are getting.
Paste each quote into the Quote Checker to compare line items before you sign.
DIY vs hiring a pro
Furnace replacement is strictly a job for a licensed, insured HVAC contractor. Gas connections, combustion venting, and carbon-monoxide safety controls all carry serious risk, and the work requires a permit and inspection in nearly every jurisdiction. Homes built before 1978 may have lead paint disturbed by ductwork changes (EPA lead-safe rules apply to contractors); homes built before the 1980s may have asbestos on old duct insulation — mention either to your contractor.
What you can do: check the age and condition of your furnace (most last 15–20 years), get three itemized quotes, and ask every bidder the same questions: What Manual J size did you calculate? What efficiency did you quote and why? What venting and condensate work is included? Is the permit included?
How to save
- Replace on your schedule, not the furnace's. A 20-year-old furnace that still runs is a project you can bid out; a dead furnace in January is an emergency purchase.
- Consider the whole system. If the AC is nearly as old as the furnace, replacing both together is often cheaper than two separate jobs — and matched systems are more efficient. Our HVAC calculator covers the full-system number.
- Check rebates before you buy. Utility and state rebates for high-efficiency equipment change often; check your utility and energystar.gov rather than relying on what a quote claims.
- Don't overbuy efficiency for a short stay. A 98% AFUE modulating furnace can take a decade or more to pay back over an 80% unit in a mild climate or a house you plan to sell soon.
- Compare scope, not just price. Two quotes can differ by $3,000 on the same equipment because one includes ductwork fixes, a liner, and a permit and the other doesn't.
Permits and timeline
A mechanical permit is required for furnace replacement in most jurisdictions, with an inspection afterward — the inspection catches venting and combustion-air mistakes, so treat it as protection, not paperwork. The install itself usually takes one day for a like-for-like swap, or two days if ductwork, venting, or fuel changes are involved. Equipment lead time is typically a few days to two weeks in the off-season; during a cold snap, expect longer waits and higher prices.